can someone help with this quest....

bedlinen p/l produces cotton sheets. B's costs of production are:

quantitity of sheets (per hour) total cost (per hour)
0 6
1 10
2 12
3 21
4 38
5 56
6 82
7 112

at an output of 4 sheets per hour, bedlinen's AFC is?

a) 1.50

can someone explain how this occurs
 

kaitoufion

Member
Joined
Dec 18, 2004
Messages
109
Location
Sydney
Gender
Female
HSC
2004
Quantity (Qd) = 4
Total Cost (TC) = 38

Then...
Total Fixed Cost (TFC) = 6

Therefore...
AFC = TFC/Qd
= 6/4
= 1.50

That's why the answer is (a).
 

tempco

...
Joined
Aug 14, 2003
Messages
3,835
Gender
Male
HSC
2004
kaitoufion said:
Quantity (Qd) = 4
Total Cost (TC) = 38

Then...
Total Fixed Cost (TFC) = 6

Therefore...
AFC = TFC/Qd
= 6/4
= 1.50

That's why the answer is (a).
thanks for that. couldnt figure out what the tfc was... damn obvious :D
 

kaitoufion

Member
Joined
Dec 18, 2004
Messages
109
Location
Sydney
Gender
Female
HSC
2004
This question is from the Sample Paper right?
I did that about 2 days ago and I think some of the questions are so hard! >_<
I couldn't even find some of the answers from the textbook that we are using.
 

Users Who Are Viewing This Thread (Users: 0, Guests: 1)

Top